View Amendment Current Amendment: 5 to Bill 4421 Rep. FORRESTER proposes the following Amendment No. 5 to H. 4421 (COUNCIL\ZW\4421C007.GGS.ZW18):

Reference is to Printer's Date 3/7/18-H.

Amend the bill, as and if amended, Section 58-40-20, as contained in SECTION 4, Page 4421-11, beginning on Line 9, by striking SECTION 4 in its entirety and inserting:

/      SECTION      4.      Section 58-40-20 of the 1976 Code is amended to read:

     "Section 58-40-20.      (A)      Net energy metering rates approved by the commission under the terms of this chapter shall must be the exclusive net energy metering rates available to customer-generators. Upon commission approval, such the net energy metering rates shall supersede all prior net energy metering rates. Customer-generators whose net energy metering facilities were energized prior to the availability of net energy metering rates approved by the commission under the terms of this chapter may remain in historic net energy metering programs through December 31, 2020. Customer-generators whose net metering facilities were energized prior to the effective date of this act under net energy metering rates approved by the commission pursuant to the terms of this chapter and in Order 2015-194 may remain in effect through December 31, 2025.
     (B)      An electrical utility shall make net energy metering available to customer-generators on a first-come, first-served basis until the total nameplate generating capacity of net energy metering systems equals two four percent of the previous five-year average of the electrical utility's South Carolina retail peak demand. No An electrical utility shall must not be required to approve any an application for interconnection from net energy metering customer-generators if the total rated generating capacity of all applications for interconnection from net energy metering customer-generators already approved to date by the electrical utility equals or exceeds two four percent of the previous five-year average of the electrical utility's South Carolina retail peak demand.
     (C)      If determined to be prudent by the commission, the electrical utility may furnish, install, own, and maintain metering equipment needed to measure the kilowatt-hours purchased by the customer-generator from the utility, the kilowatt-hours generated or delivered to the electrical utility, and, if applicable under the utility's tariffs, to measure the kilowatt demand delivered by the electrical utility to the customer-generator. The electrical utility shall have has the right to install special metering and load research devices on the customer-generator's equipment and the right to use the customer-generator's communication devices for communication with electrical utility's and the customer-generator's equipment.
     (D)      The net electrical energy measurement shall must be calculated in the following manner:
           (1)      For a customer-generator, an electrical utility shall measure the net electrical energy produced or consumed during the billing period in accordance with normal metering practices for customers in the same rate class, either by employing a single, bidirectional meter that measures the amount of electrical energy produced and consumed, or by employing multiple meters that separately measure the customer-generator's consumption and production of electricity;. Each kilowatt-hour of electricity generated by the customer-generator must be valued, accounted for, and credited at the utility's avoided cost;
           (2)      If the electricity supplied by the electrical utility exceeds the electricity generated by the customer-generator during a billing period, the customer-generator shall must be billed for the net electricity supplied by the electrical utility in accordance with normal practices for customers in the same rate class;
           (3)      Any energy generated by the customer-generator that which exceeds the energy supplied by the electrical utility during a billing period shall must not be used to offset the nonvolumetric electricity charges for that billing period;
           (4)      The utility shall maintain an account of any net excess kWh credits accruing from the customer-generator's excess generation and allow those kWh credits to be used to offset the customer-generator's energy usage during future billing periods at the utility's avoided cost. Annually, the utility shall pay the customer-generator for any accrued net excess generation at the utility's avoided cost for qualified facilities, zeroing out the customer-generator's account of net excess kWh credits.
     (E)      Each electrical utility shall submit an annual net metering report to the Public Service Commission, with a copy to the Office of Regulatory Staff, including the following information for the previous calendar year:
           (1)      the total number of customer-generator facilities;
           (2)      the estimated gross generating capacity of its net-metered customer-generators;
           (3)      the estimated net kilowatt hours received from customer-generators.
     (F)      Any and all costs prudently incurred pursuant to the provisions of this chapter by an electrical utility as approved by the commission and any and all commission approved benefits conferred by a customer-generator shall must be recoverable by each entity respectively in the electrical utility's rates in accordance with these provisions:
           (1)      The electrical utility's general rates, tariffs, and any additional monthly charges or credits, in addition to any other charges or credits authorized by law, to recover the costs and confer the benefits of net energy metering shall include such the measures necessary to ensure that the electrical utility recovers its cost of providing electrical service to customer-generators and customers who are not customer-generators.
           (2)      Any charges or credits prescribed in item (1), and the terms and conditions under which they may be assessed shall must be in accordance with a methodology established through the proceeding described in item (4). The methodology shall must be supported by an analysis and calculation of the relative benefits and costs of customer generation to the electrical utility, the customer-generators, and those customers of the electrical utility that who are not customer-generators.
           (3)      Upon approval of the methodology provided for in item (4), each electrical utility shall file its analysis of the net cost to serve customer-generators using the approved methodology and shall propose new net energy metering rates.
           (4)      No later than thirty days after the enactment of this act, the commission shall initiate a generic proceeding for purposes of implementing the requirements of this chapter with respect to the net energy metering rates, tariffs, charges, and credits of electrical utilities, specifically to establish the methodology to set any necessary charges and credits as required under items (1) and (2). All interested parties shall must be allowed to participate. In its notice initiating such the proceeding, the commission must require the electrical utilities to propose methodologies required by item (1) and shall allow intervening parties to propose methodologies required by item (2). The Office of Regulatory Staff, pursuant to the requirements of Section 58-4-50, shall represent the public interest in this proceeding and shall serve as a facilitator to resolve disputes and issues between the parties to this proceeding.
           (5)      In evaluating the benefits and costs of customer generation as required by item (2), and the methodology for calculating such the benefits and costs, the Office of Regulatory Staff may engage third parties with relevant prior experience conducting distributed generation cost-benefit studies. The cost of any experts and consultants engaged by the Office of Regulatory Staff for purposes of this proceeding shall must be assessed to the electrical utilities pro rata based on their five-year average of retail peak demand and shall be are recoverable by those electrical utilities through the base rate for fuel costs established pursuant to Section 58-27-865.
           (6)      In the event that the commission determines that future benefits from net energy metering are properly reflected in net metering rates because they provide quantifiable benefits to the utility system, its customers, or both, and to the degree such these benefits then are not then being recovered by the electrical utility in its base rates, then such the future benefits shall must be deemed an avoided cost and shall be are recoverable pursuant to Section 58-27-865 by the electrical utility as an incremental cost of the distributed energy resource program.
           (7)      Notwithstanding another provision of law, customers of the utility who are not customer-generators are not required to subsidize the costs of customer-generators.
     (G)      In no event shall the net energy metering provisions of this chapter be construed as allowing customer-generators to engage in meter aggregation, group/joint group or joint billing projects, and/or or virtual net metering.
     (H)      The commission shall approve an electrical utility's proposed net energy metering rates that meet the requirements of this chapter, provided that the commission has previously approved that electrical utility's application to participate in a distributed energy resource program pursuant to Chapter 39, Title 58."      /

Amend the bill further, as and if amended, by adding an appropriately numbered SECTION to read:

/      SECTION      ___.      Section 58-40-10 of the 1976 Code is amended by adding an appropriately lettered subsection at the end to read:

     "( )      'Avoided costs' means payments for purchases of electricity made according to an electrical utility's most recently approved or established avoided cost rates in this State or rates negotiated pursuant to PURPA in the year the costs are incurred, for purchases of electricity from qualifying facilities pursuant to Section 210 of the Public Utility Regulatory Policies Act, the costs are to be calculated as set forth in Section 58-39-140(A)(1)."      /

Renumber sections to conform.
Amend title to conform.