View Amendment Current Amendment: JUD to Bill 1077

The COMMITTEE on JUDICIARY proposed the following amendment (JUD1077.005):

Amend the bill, as and if amended, beginning on page 1, line 29, and ending on page 2, line 3, by striking Section 58-27-1100, and inserting:

/ Section 58-27-1100.Upon application by an electrical utility, the commission may by order authorize the issuance of bonds for the purposes of offsetting and reducing prudently incurred costs due to storm recovery activity. It is in the interest of the State and its citizens to encourage and facilitate the use of securitized bonds as a method for enabling electrical utilities to lower the cost of financing the costs of these activities under certain conditions, and to empower the commission to review a securitization mechanism to determine whether it is consistent with the public interest and worthy of approval. In order for the commission to authorize the issuance of these bonds, it must find that an electrical utility's use of this financing mechanism will provide quantifiable net benefits to customers on a present value basis as compared to the costs that would have been incurred absent the issuance of storm recovery bonds, and will result in the lowest storm recovery charges consistent with market conditions at the time the storm recovery bonds are priced and the terms set forth in a financing order issued by the commission. /

Amend the bill further, as and if amended, page 3, by striking lines 32-39, and inserting:

/ (13 )(a) The term 'storm recovery activity' means an activity or activities by an electrical utility, its affiliates, or its contractors directly and specifically in connection with the restoration of service and infrastructure associated with electric power outages affecting customers of an electrical utility as the result of a storm or storms, including activities related to mobilization, staging, and construction, reconstruction, replacement, or repair of electric generation, transmission, distribution, or general plant facilities.

(b)No electric utility is required to securitize nor is it prohibited from securitizing those capital improvements or infrastructure upgrades that have a quantifiable net benefit to consumers and that improve the resiliency of the transmission and distribution system. /

Amend the bill further, as and if amended, page 6, by striking lines 11-20 and inserting:

/ (7) a comparison between the net present value of the costs to customers that are estimated to result from the issuance of storm recovery bonds based on current market conditions and the costs that would result from the application of the traditional method of financing and recovering storm recovery costs from customers. The comparison should demonstrate that the issuance of storm recovery bonds and the imposition of storm recovery charges are expected to provide quantifiable net benefits to customers on a present value basis as compared to the costs that would have been incurred absent the issuance of storm recovery bonds; and /

Amend the bill further, as and if amended, page 12, by striking lines 3-20 and inserting:

/ (B) The commission may not order or otherwise directly or indirectly require an electrical utility to use storm recovery bonds to finance any project, addition, plant, facility, extension, capital improvement, equipment, or any other expenditure except as permitted under this article. After the issuance of a financing order, the electrical utility retains sole discretion regarding whether to cause the storm recovery bonds to be issued, including the right to defer or postpone such sale, assignment, transfer, or issuance , unless otherwise provided in the financing order. Nothing shall prevent the electrical utility from abandoning the issuance of storm recovery bonds under the financing order by filing with the commission a statement of abandonment and the reasons therefor. The commission may not refuse to allow an electrical utility to recover storm recovery costs in an otherwise permissible fashion, or refuse or condition authorization or approval of the issuance and sale by an electrical utility of securities or the assumption by the electrical utility of liabilities or obligations, solely because of the potential availability of storm recovery bond financing. /

Amend the bill further, as and if amended, page 17, by striking lines 18-35 and inserting:

/ (3) Any right that an electrical utility has in the storm recovery property before its pledge, sale, or transfer or any other right created under this article or created in the financing order and assignable under this article or assignable pursuant to a financing order is property in the form of a contract right or a chose in action. Transfer of an interest in storm recovery property to an assignee is enforceable only upon all of the following items having been attained: (i) the issuance of a financing order, (ii) the assignor having rights in such storm recovery property or the power to transfer rights in such storm recovery property to an assignee, (iii) the execution and delivery by the assignor of transfer documents in connection with the issuance of storm recovery bonds, and (iv) the receipt of value for the storm recovery property. An enforceable transfer of an interest in storm recovery property to an assignee is perfected against all third parties, including subsequent judicial or other lien creditors, when a notice of that transfer has been given by the filing of a financing statement in accordance with item (B)(3) of this section. The transfer is perfected against third parties as of the date of filing. /

Amend the bill further, as and if amended, page 18, by striking lines 41-43 and inserting:

/ Section 58-27-1135.All financing statements referenced in this article are subject to Part 5 of Chapter 9 of the Code, except that the requirement as to continuation statements does not apply. /

Amend the bill further, as and if amended, page 20, by striking lines 28-30 and inserting:

/ (B) Any person or entity that issues storm recovery bonds may include the language specified in this section in the storm recovery bonds and related documentation. /

Amend the bill further, as and if amended, page 20, by striking lines 35-39 and inserting:

/ Section 58-27-1165.If there is a conflict between this article and any other law regarding the attachment, assignment, perfection, effect of perfection, priority of, assignment or transfer of, or security interest in storm recovery property, this article shall govern. /