Part 1B SECTION 88 - Y140 - STATE PORTS AUTHORITY
2019-2020 Appropriation Act


SECTION 88 - Y140 - STATE PORTS AUTHORITY

 

88.1. (SPA: Charleston Cooper River Bridge Project) The State Ports Authority shall, from other general fund or operating fund surplus available and any funds appropriated to the authority in prior fiscal years and left unexpended as of July 1, 2019, pay to the State Transportation Infrastructure Bank one million dollars before June 30, 2020, to continue the Charleston Cooper River Bridge Project.

88.2. (SPA: Georgetown Port Marketing) The State Ports Authority will continue its cargo diversification strategy which enhances the marketing of all terminal capabilities in Charleston and Georgetown highlighting cruise, breakbulk, bulk, and roll on/roll-off.

88.3. (SPA: Harbor Deepening Reserve Fund) The State Ports Authority shall maintain the Harbor Deepening Reserve Fund. This fund shall be separate and distinct from the General Fund and interest accrued by the fund must remain in the fund. This fund must be used exclusively by the South Carolina Ports Authority for the activities associated with deepening the states harbors. Prior to expending any amount from the fund, the State Ports Authority must present a comprehensive plan for the use of the fund for harbor deepening to the Joint Bond Review Committee for review and comment. These funds shall be carried forward from the prior fiscal year into the current fiscal year and must be used for the same purpose.

88.4. (SPA: Georgetown Port Maintenance Dredging Fund) The State Ports Authority shall maintain the Georgetown Port Maintenance Dredging Fund and any funds appropriated in this act for this purpose shall be deposited into this account. This fund shall be separate and distinct from the General Fund and the Harbor Deepening Reserve Fund and interest accrued by the fund must remain in the fund. This fund must be used exclusively by the South Carolina Ports Authority for the activities associated with the maintenance dredging of the Port of Georgetown. Prior to expending any amount from the fund, the State Ports Authority must present a comprehensive plan for the use of the fund for maintenance dredging to the Joint Bond Review Committee for review and comment. These funds shall be carried forward from the prior fiscal year into the current fiscal year and must be used for the same purpose.

88.5. (SPA: Jasper Ocean TerminalNext Permitting) From funds specifically appropriated to the State Ports Authority (SPA) for the PreviousJasper Ocean TerminalNext, not more than $5,000,000 shall be spent on the purchase of real property as may be available for purchase through that certain Option Agreement by and between Sherwood Plantation, Inc., and Southern Carolina Regional Development Alliance (SCRDA) dated September 20, 2017, as may be amended, so long as SCRDA secures the right to and assigns said Option Agreement to the SPA no later than September 30, 2019. In no event and under no circumstance shall the cost, expense, purchase price, payments, fees, or any associated charges for the acquisition of such property cause the SPA to expend more than the $5,000,000 appropriated for this purpose. It is understood that this limitation shall result in less than the full acreage currently under option being purchased by the SPA.

Should the Option Agreement be exercised by the SPA, then SPA shall take title and include in the deed language providing that such property purchased pursuant to the Option Agreement shall be transferred to Jasper County by operation of law in the event that upon the fifth anniversary of the closing on such property the property has not been sold, leased, or otherwise utilized for an economic development project that will utilize port facilities. The intent of such condition is to develop the property in a manner that highlights the necessity of the PreviousJasper Ocean TerminalNext.

Any funds appropriated to the (SPA) for the PreviousJasper Ocean TerminalNext remaining after the exercise of and purchase of real property pursuant to the Option Agreement or in the event the SCRDA does not assign the Option Agreement by September 30, 2019, shall be utilized by the SPA to pay for activities approved and directed by the joint venture governing board and associated with advancing the Project during FY 2019-20. In connection with activities that are approved and directed by the joint venture, SPA shall comply with the directive of Section 54-3-115 of the South Carolina Code in regard to taking all action necessary to expeditiously develop a port in Jasper County. Activities undertaken during FY 2019-20 may include, but are not limited to, the following:

1. working on a corporate governance model for the joint venture as an operating port;

2. working on terminal simulation for design and operation;

3. working on plans, studies, and modeling in conjunction with the respective South Carolina and Georgia Departments of Transportation and the metropolitan planning organization to identify and assess supporting road and rail infrastructure for the terminal footprint including, but not limited to, supporting infrastructure that may have independent utility;

4. working on sedimentation modeling for impacts on construction and dredging;

5. taking actions in furtherance of obtaining: (a) a Department of the Army permit pursuant to Section 10 of the Rivers and Harbors Act; (b) a permit pursuant to Section 404 of the Clean Water Act, to prepare a Channel Modification Feasibility Study; and (c) studies necessary in connection with developing an Environmental Impact Statement for the Project; and

6. discharging its obligations pursuant to its Joint Venture Agreement with the Georgia Ports Authority.

The funds appropriated to SPA for the PreviousJasper Ocean TerminalNext Permitting may not be used for reimbursement of SPA expenditures made in a prior fiscal year and must be used only for one or more of the purposes set forth above.

SPA shall provide a detailed report in writing to the members of the South Carolina General Assembly on or before the first day of the 2020 legislative session and another such report on or before June 30, 2020, describing the progress made as of the dates of those reports in regard to the PreviousJasper Ocean TerminalNext, such to include a description of the ongoing and planned work.

88.6. (SPA: PreviousJasper Ocean TerminalNext Port Facility Infrastructure Fund) There is created within the State Ports Authority the PreviousJasper Ocean TerminalNext Port Facility Infrastructure Fund. The State Ports Authority shall maintain the PreviousJasper Ocean TerminalNext Port Facility Infrastructure Fund and any funds appropriated in this act for this purpose shall be deposited into this account. This fund shall be separate and distinct from the General Fund and interest accrued by the fund must remain in the fund. This fund must be used exclusively by the State Ports Authority for activities associated with the development of the PreviousJasper Ocean Terminal Port facility and infrastructure necessary to support the facility. These funds shall be carried forward from the prior fiscal year into the current fiscal year and must be used for the same purpose.

 